Application:
New water treatment plant designed to double the area’s water output from 4 to 8 million gallons per day. Pre-treatment of water was changing from chlorine to ozone using liquid oxygen.
Project Background:
Chart was requested to develop the cryogenic liquid oxygen (LOX) storage system and was depended upon to advise the end-user on selection of components for the Duchesne Valley plant.
Significant Accomplishments:
Chart was able to accommodate some unusual requests in the design. The plant required very specific electric-actuated valves (instead of the typical air-actuated valves). Chart’s engineers worked with the client to help them implement custom piping using T316 steel for all tubing and piping as site specific requirements upgraded from T304 standard.
The ozone generation system was completed as promised, and within budget.
System Configuration:
Chart’s (1) 6,000 gallon vessel and components for a turnkey solution was plugged seamlessly into the entire water treatment system. The Contractor has a single-source accountability for their entire oxygen supply system. All components were factory tested and designed for ease of installation.
Full factory built skid module designs reduced the on-site install effort and eliminated fighting with field installation issues.
Highlights:
Location – Duchesne County, Utah
Scope of Project: